Energy · Case 08 · Example
Power plant cooling runs hot.
About 40 MW will be missing in the bottleneck from 18:00. The cooling water is 4 K too warm, and unit 2 cannot go above about 220 MW. The grid operator calls 260 MW for 18:00. Quantryx links the two at 15:44.
- 2signals from Operations, IT
- 15:44Parallax links them
- 3options to decide

How the case unfolded
The control room knows the limit, dispatch planning the call.
- OperationsCooling water 31 °C, unit 2 up to about 220 MW
- ITRedispatch call: unit 2 to 260 MW from 18:00
- ParallaxWith 31 °C cooling water unit 2 manages about 220 MW, and it stays hot and humid until about 21:00. About 40 MW of the call are missing, about 120 MWh from 18:00 to 21:00. The call rests on planning data from 15:00, when 260 MW were still right.
What needs deciding now
Where do the about 40 MW come from at 18:00 that unit 2 cannot deliver?
- A
Report back
From 18:00 unit 2 runs up to its limit, about 220 MW. At about 15:50 dispatch planning reports about 40 MW as unavailable from 18:00 to 21:00. The grid operator has about 2 h for a replacement, which is usually farther from the bottleneck and less effective; grid customers bear the cost.
Replacement with about 2 h lead · cost to grid customers
- B
Mix in river water
From about 17:30 the cooling water drops to about 28 °C, unit 2 manages about 260 MW, and the gap is about 0 MW. Below the outfall the river is above 28 °C from about 19:00, and oxygen falls. This needs an exemption from the water authority.
Gap about 0 MW · river above 28 °C from about 19:00
- C
Interrupt the overhaul (grid operator)
The crew clears the work site, the North circuit is back in service at about 17:45, and the call is withdrawn. The overhaul must be replanned, with about 2 days of work and a new outage. This only works if the state of the work allows switching back on.
No bottleneck · overhaul about 2 days back
Sign-offPower plant shift lead with dispatch planning (A) or with the water protection officer (B); the water authority grants the exemption. The grid operator decides C and switches back on by switching order once the work site is cleared. The grid operator is informed in every case.
An example with invented data, not a customer case. Times, numbers and consequences are estimates within the example.